Total remodeling work was carried out on this property.

Our design department developed a design with 2 bathrooms, 1 WC, 2 bedrooms and a separate laundry room.

Indicatively, the works carried out at the property are:

  • Removal of a large part of the masonry.
  • Construction of new masonry.
  • Ceiling construction using drywall with spot and concealed lighting.
  • New total installation of heating piping using multilayer pipes.
  • New total electrical installation including new power and lighting supplies, DATA network and alarm wiring.
  • Supply and installation of tiles and sanitary ware in the bathrooms.
  • Placement of solid wood flooring.
  • Sanding and polishing of wooden floors.
  • Supply and installation of aluminium frames with four-season energy glazing and electric shutters.
  • Supply and installation of wardrobes, kitchen, internal doors and security door.
  • Application of two layers of acrylic putty on all surfaces of the house and painting with ecological paints of the company VIVECHROME.

 

Project completion time: 50 days